The crane stood on the end of the unfinished bridge, its boom leaning out over the drop, and lowered one fifty-ton block of concrete after another out across a field of boulders. Below it, the rocks lay the way they had for thousands of years, with rhododendron growing in the gaps between them, untouched. The men in hard hats standing on the edge of the deck were tiny against the mountain. Somewhere far beneath them, the last gap in a road 469 miles long was closing, a road that had been started almost half a century before and that two generations of builders had fought the mountains over.

The machine reached out again, swung a segment past the edge, and held it against the face of the last one placed. Epoxy glue went on the joint, steel tendons were pulled tight, and another piece of the bridge became part of the whole. Then the crane rolled forward onto the segment it had just set and reached for the next one. There was no ground beneath any of it.
No scaffolding climbed up from below. No truck drove under the work. The only place anybody touched the mountain was at the foot of each pier, and even those were drilled down through the boulders into the solid rock underneath. They called it the Linn Cove Viaduct, a pale gray ribbon of concrete curling around Grandfather Mountain in the shape of an S, hanging in the air on thin piers.
It was the last piece of the Blue Ridge Parkway, and the whole road took fifty-two years to finish. In the fall of 2024, a single storm closed every one of those 469 miles at once. Two people walk through this story. One is Stanley Abbott, a landscape architect in his twenties, three years out of Cornell, handed a blank map of the Southern Mountains in December of 1933 and told to design a road nobody had ever built.
The other is Rex Kraftoft, a federal highway engineer who, almost fifty years later, had to watch over a bridge being built out into thin air from its own front edge. Between the first shovel and that last block of concrete, the mountains pushed back five times. First a ridge that two states fought over. Then a summer storm that tore the new road off the hillsides.
Then a war that froze a third of the route half-finished. Then a mountain whose owner would not let the road go over the top. And last of all, a field of loose boulders that no ordinary road could cross. It started on a Wednesday morning in a gap in the hills just south of the Virginia line.
The place was called Low Gap in Alleghany County, North Carolina, close to a rounded little summit named Cumberland Knob. On September 11th, 1935, men hired off the county’s relief rolls began unloading heavy machinery there and dragging it into position. The contract for the first stretch of road, about twelve and a half miles of it, belonged to a Durham builder named Neil Turrentine. The plan was simple.
The steam shovels would start moving dirt on Monday morning, September 16th. They didn’t. The machines were still being set, and the first real breaking of ground on the first project of the Blue Ridge Parkway did not happen until Thursday, September 19th. The road that would someday take fifty-two years to finish began by running eight days late on its very first job.
Eight days is nothing on a road that long, but it tells you what kind of ground they were standing on and what kind of men were standing on it. Most of the crew that unloaded those machines had come off the county’s relief rolls in the middle of the Depression. The parkway was meant to carry tourists someday. That fall, it was carrying paychecks.
In that country, nothing moves on schedule. Every machine has to be walked in over farm tracks. Every load of fuel comes up a grade, and the next hill is always steeper than the one the surveyors drew. And the strange part is that the road was designed to make that harder on purpose.
Think about how you’d build a highway if all you wanted was to get from one end to the other. You’d find the valleys, follow the rivers, cut through the ridges, and fill the hollows, and keep the line as straight and level as the money allowed. That’s what highway engineers in the 1930s were trained to do. Stanley Abbott was told to do the opposite.
The road would ride the crest of the mountains, up where the views were, and it would go around things instead of through them whenever it could. It would bend with the ridge, rise and fall with it, and stay narrow and low, so that from a mile away it nearly disappeared into the trees. That sounds backward when you say it out loud. A road built to be longer, slower, and harder to build than it needed to be.
But that was the whole idea. Abbott’s rule, as the park service still describes it, was to fit the road into the mountains so it looked like it belonged there, as if it had always been part of them. It’s like sewing a seam along a crease in a sheet of paper instead of across it. Follow the crease and you hardly see the stitches.
Cross it and you leave a scar. Abbott wanted the stitches to follow the crease for more than 400 miles. Which raises a question. Who decided where the crease even was?
A North Carolina highway engineer named R. Getty Browning did mostly, and he did it on foot, walking the ridge lines mile after mile with a notebook in 1934, picking out the line that would hold the views. Tennessee wanted the southern half of the road on its side of the mountains instead. On June 13th, 1934, a federal committee agreed with Tennessee.
Then on November 10th, the Secretary of the Interior, Harold Ickes, overruled his own committee and gave the line Browning had walked to North Carolina. That’s why the Parkway spends most of its miles in North Carolina and why it climbs so high there. And the ridge Browning had picked so carefully was the same ridge that would fight the builders hardest. The way they attacked it was to break the road into pieces.
The Parkway was not built as one long project. It was cut into forty-five separate construction units, each with its own contract, its own crews, and its own start date. Part of that was because the land came in slowly. The states had to buy the right-of-way farm by farm, and a unit could not begin until every parcel along it was in hand.
But part of it was deliberate. Forty-five jobs meant crews could work in many places at once, and in 1935 that meant more people with a paycheck. On June 30th, 1936, Congress made it official, gave the road its name, the Blue Ridge Parkway, and put it in the hands of the National Park Service. When Ickes had first approved the idea on November 24th, 1933, the budget for the entire road had been $16 million.
Remember that number. It’s going to look very small by the end of this story. The road itself went to contractors like Turrentine with steam shovels and dump trucks, and to crews from the Works Progress Administration. The Emergency Relief Administration did landscape work along the edges.
And four camps of the Civilian Conservation Corps were set up on or near the parkway, where young men did roadside cleanup, planting, and the grading of slopes so the raw cuts would heal into the hillsides. That last job matters more than it sounds. On most highways of the time, when you blasted a cut through a ridge, you left the scar. On the parkway, the cut banks were rounded off and planted so they would look like the mountain had settled that way on its own.
The guard walls, the culverts, and the bridges were faced with stone taken from the ground right there, laid by masons, so the stone matched the rock it was cut from. A road that looked effortless was costing extra effort at every single bend, and Abbott was the man responsible for all of it. In March of 1937, still in his twenties, he was named resident landscape architect and acting superintendent of the entire parkway. Here’s the problem with building a road along the top of a ridge.
On a valley road, the water is below you. It runs off the pavement into a ditch and down to the river, and the river carries it away. Up on a crest, the road sits across the slope. Every bit of rain that falls on the mountain above it comes downhill, hits the road, and has to go somewhere.
If it can’t get under the road, it goes across it. And if it goes across it often enough, it takes the road with it. Picture what a single mile of that took in 1936. The surveyors staked the line along the slope.
Then a steam shovel bit into the uphill side and swung the rock and dirt across to the downhill side, so the road would sit on a shelf that was half cut into the mountain and half built out from it. Where the slope was solid rock, the crews drilled and blasted first, and the shovel came in behind them. The fill had to be packed in layers or it would slump the first time it got wet. And every bit of it was done on a grade where a dump truck that lost its brakes had nowhere to go but down.
It’s like carving a step into the side of a sand dune and then trying to stand on it. The step is only as good as the sand under the half you added. So for every mile of pavement, the crews also had to build a hidden second road for water. Culverts under the grade, ditches on the uphill side, stone-lined outlets on the downhill side, so the water would leave without carving the slope away.
Most of it you never see when you drive the parkway today. But it was some of the hardest work on the whole job, because a road on a mountain side lives or dies by where its water goes. And on the first sections, the water didn’t always go where it was meant to. On some stretches, drainage that hadn’t been laid quite right was already cutting gullies along the new road.
In a normal summer, that’s a maintenance job. A crew comes out with shovels and a few loads of rock. By the summer of 1940, the parkway was taking shape in pieces up and down the ridge. Stretches were open and carrying cars in Virginia and in North Carolina, and others were graded and waiting for their surface.
Tourists were already pulling over at the new overlooks to look out over the hollows. The weather that August didn’t look like anything special at first. A tropical storm had come ashore on the Atlantic coast and was dying as it moved inland, the way storms usually do. But this one stalled over the mountains of western North Carolina and stayed there.
On the evening of August 13th, 1940, in the mountain town of Boone, in the same high country where the Parkway’s last gap would one day sit, the rain gauge recorded two inches between five and six o’clock. In one hour. And it didn’t stop. Over the next forty-eight hours, the area around Boone took about eight inches.
At a place called Idlewild, the gauge caught more than twenty inches. The ground on those mountain slopes was thin soil over rock, and once it was full of water, it simply let go. In Watauga County alone, the storm set off more than 2,000 landslides. Sixteen people in that county died.
Across the region, the count reached about fifty. Bridges went out on nearly every road into Boone. The telephone lines went down, and the town was cut off from the outside world for days. The little railroad that had served Boone never ran there again.
And up on the ridge, the new parkway was caught right in the middle of it. The park service sent a photographer out the moment anyone could move. On August 16th, 1940, the camera stopped at milepost 320, in a construction section the engineers called 2K, where a whole piece of the mountain had slid down across the new road. The next day, August 17th, a man named A.
S. Burns was out photographing the damage from milepost 237 to milepost 248. Fallen trees, washed-out shoulders, slides one after another across the roadway. Those photographs still exist, and what they show is a road that had done exactly what Abbott designed it to do.
Laid gently along the slope, now with the slope coming down on top of it. That’s the cruel part of building along a ridge. The road is in the one place where the whole mountain’s water and soil have to cross it. In a storm like that one, there is no place on the hillside a road can hide.
The crews went back to the drainage. Slides were cleared, slopes were rebuilt, and the lesson of those gullies went into every section that came after it. The parkway that survived 1940 was built to move water harder than the one before it. But the next thing to stop the road wasn’t water.
It was a world war. When the United States entered the Second World War, the Blue Ridge Parkway was about a third of the way to being a real road and about two-thirds of the way to being a promise. Roughly 170 miles were open to travel, and about 160 more were under construction, graded, half-graded, or waiting on bridges. Then the money went to the war, and the men went with it.
The relief programs that had supplied so many of the workers were shut down one after another. By 1943, construction on the Parkway had come to a halt for the duration. Think about what that looked like on the ground. 160 miles of unfinished road scattered in pieces along the ridge.
Raw cuts that hadn’t been planted. Fills that settled. Drainage ditches with no one to keep them clear. All of it sitting out in the mountain weather year after year with nobody to defend it.
And everybody on the Parkway had seen in August of 1940 what the mountain weather could do to a road nobody was guarding. Somebody still had to look after it. During the war, the camps of young men who had been doing the slopes and planting were replaced by a very different crew. They were conscientious objectors, men who had refused to fight on grounds of conscience, assigned to what was called Civilian Public Service.
Some of them were sent to the parkway to do landscape and park work along the very road the war had stopped. Those men left a mark you can still find. The Civilian Public Service camps were run largely by the historic peace churches, the Mennonites, the Brethren, and the Quakers, and the men who served in them worked without wages. So in the middle of the war, the people keeping the Blue Ridge Parkway alive were men who had said no to the war.
They couldn’t build the road, but they could keep the mountains from taking back the pieces that already existed. When the war ended, the builders came back, and the road didn’t come back with them. Workers returned slowly. New machinery was hard to get, because every factory in the country had been building for the war.
By the early 1950s, the park service’s own count was that only about half of the Blue Ridge Parkway was finished. Half, after more than fifteen years. At that speed, the road would not be done until somewhere near the end of the century. And the half that was left was the hard half.
What saved the schedule was a deadline nobody in the mountains had asked for. In the middle of the 1950s, the National Park Service launched a ten-year building program called Mission 66. It was timed to finish in 1966, the fiftieth birthday of the park service itself, and it poured money into roads, visitor centers, and campgrounds in parks all over the country. One of its goals was to get the Blue Ridge Parkway finished by that date.
Now the road had a clock. Ten years to build the half of it that had defeated the builders for twenty. The trouble was where that half was. The easy sections, the rolling ridges in Virginia and the gentler country near the state line, had gone first.
What was left lay in the high country of North Carolina, where the Blue Ridge breaks up into a tangle of separate ranges: the Blacks, the Craggies, the Great Balsams, with peaks well over 6,000 feet. Up there, a ridge doesn’t run in a clean line for long. It stops, and the road has to get to the next one. And when a road can’t go around a mountain, and the rules say it can’t cut the mountain open, there’s only one way left.
It goes through. The parkway has twenty-six tunnels. One of them, Bluff Mountain, is in Virginia. The other twenty-five are all in North Carolina, and most of them were bored in the late 1940s and the 1950s as the road pushed into that high country.
The way they did it was slow, loud work. Drillers rode a rig they called a jumbo, a platform on a truck bristling with water-cooled drills. They’d roll the jumbo up to the rock face and drill a pattern of holes deep into the stone. Then the jumbo backed out, the holes were packed with dynamite, and the face was blown.
Crews mucked out the broken rock. The jumbo rolled back in. And they did it again. On a good stretch, a crew might gain about ten feet a day.
Ten feet a day is about the length of a small car, with the whole mountain sitting on top of you. The longest of the parkway’s tunnels is the Pine Mountain Tunnel south of Asheville, at 1,434 feet. At ten feet a day, a single crew driving from one face would need well over four months to get through it. Others are tiny by comparison.
The Craggy Pinnacle Tunnel near the Craggy Gardens is only 176 feet long. But a short tunnel through a mountain peak is still a tunnel, and every one of them was blasted and mucked out a few feet at a time. A tunnel also did something a cut never could. Blast a cut through a ridge and you leave a notch in the skyline that you can see for miles.
Bore through it and the ridge above stays whole, with the trees still standing on top, as if the road weren’t there at all. Once each tunnel was through, its portals were faced in stone, so the hole in the mountain looked as if it had grown there. Abbott’s rule followed the road even underground. The clock kept running through the late fifties and into the sixties.
The gaps closed one by one. The sections around the city of Asheville were among the last of the long stretches to be finished in the 1960s, sweeping around the city on the high ground and threading the tunnels south toward the Smokies. By the end of 1966, the Mission 66 deadline, the Blue Ridge Parkway was complete. Almost.
Out of 469 miles, everything was done except 7. 7 miles. One short piece of road on the side of one mountain in Avery County, North Carolina. A driver heading south along the parkway reached the base of Grandfather Mountain and was sent off the Parkway onto an ordinary highway, US 221, to wind around the mountain before getting back on the other side.
Seven miles out of almost 500. It should have taken a season. Instead, it took twenty more years. To understand why, you have to look at the mountain itself.
Grandfather Mountain is one of the most rugged peaks in the southern Appalachians, a long, jagged crest of bare rock standing above the Linville country. It’s steep, it’s broken, and its upper slopes are covered in loose fields of boulders, rock that has been sliding and settling down the mountain since long before anybody thought of a road. And it wasn’t public land. It belonged to the family of a man named Hugh MacRae, through a company called the Linville Company.
Back in the 1930s, the state of North Carolina had paid that company for a right-of-way along the lower route, the one where 221 already ran. Then, in the late 1940s, the land passed to MacRae’s grandson, Hugh Morton, back from service in the Second World War. Morton built a toll road up the mountain, and in 1952 he opened a suspension footbridge between two peaks near the top and called it the Mile High Swinging Bridge. Grandfather Mountain became one of the best-known attractions in the North Carolina mountains.
Meanwhile, the park service had decided the lower route along 221 wasn’t right for the parkway. Its engineers wanted a higher line, about 600 feet up the mountain from the existing highway, still several hundred feet below the summits, with a 1,700-foot tunnel through a spur called Pilot Ridge. In 1955, the state acquired that higher right-of-way by condemnation. Morton fought it, and he told the governor that a road cut across the face of his mountain would be like taking a switchblade to the Mona Lisa.
He had the governors on his side, first Luther Hodges, then Terry Sanford, then Dan K. Moore. In 1957, the state highway commission deeded the land back to him. So now there were two sides, and each one had a reason.
The park service believed its higher line was the only way to carry the parkway’s standards around that mountain, and it would not build a lesser road on its last few miles. Morton believed a highway blasted across the upper slopes would scar the very thing people came to see, and his own business along with it. Historians reading the letters from those years have found that tourism weighed on his side as heavily as scenery did. The Parkway superintendent through those years was Sam Williams, and the man handling the state’s land for the road was the same R.
Getty Browning who had walked the ridges on foot back in 1934. They kept pressing for the high line. Morton kept answering that their line meant blasting all the way across the face of the mountain. Neither side moved.
For thirteen years, the last gap in the Blue Ridge Parkway was a stalemate on paper, while every summer, thousands of cars came down the finished road and got sent off it at the foot of Grandfather Mountain. Finally, in the late 1960s, the park service accepted a line lower on the mountain than its high route. Morton called it a compromise. In 1968, construction on it began.
Most of the missing seven miles could now be built the ordinary way. Most of them, but not every mile. Because the compromise line ran straight across a place on the eastern slope called Linn Cove. And Linn Cove was the worst ground on the entire mountain.
A steep slope piled with huge loose boulders, with a fragile cover of plants and trees growing in the gaps between them. Build a normal mountain road across a slope like that, and you start by blasting a bench into it and pushing the spoil downhill. On Linn Cove, that would have torn open the boulder field from top to bottom and set the rocks above it moving. You couldn’t cut it, you couldn’t fill it, and you couldn’t haul machinery across it without crushing the very thing everybody had spent thirteen years fighting to protect.
So while the crews graded and paved the rest of the missing seven miles on either side, the stretch across Linn Cove sat empty on the map. Year after year, a road finished at both ends, with nothing in the middle but a slope of rocks. In 1975, the engineers went back to that slope to find out what was really under it. They drilled into the boulder field to see where the loose rock stopped and the solid mountain began, because whatever they built would have to stand on the solid part and leave the loose part alone.
A boulder field is exactly what it sounds like. Rocks resting on rocks, with soil and roots holding the gaps between them. Disturb the bottom of a pile like that, and the top comes down to fill the hole. The engineers looked at that slope and came to the conclusion that there was no way to build an ordinary road across it at all.
So they decided the road would never touch it. The job went to an engineering firm from Tallahassee, Florida, called Figg and Mueller. Its partners were Eugene Figg and a French engineer named Jean Mueller, and what they specialized in was a way of building bridges that was still new in America, out of precast concrete segments. Instead of pouring a bridge in place on the ground underneath it, you cast it in pieces somewhere else, carry the pieces out, and join them together in the air.
Notice what they didn’t propose. The old high route had called for a tunnel, 1,700 feet through Pilot Ridge, and tunnels were something the parkway had plenty of practice with. But a tunnel needs solid rock to hold itself up. Bore into a pile of loose boulders, and you’re not digging a tunnel.
You’re digging a cave-in. And a cut-and-fill road was out from the start. That left only one way across. Their answer for Linn Cove was a viaduct, a bridge that runs along a slope instead of across a river.
It would carry the parkway around the face of the boulder field on a curving ribbon of concrete, high enough above the rocks that the rocks could stay exactly where they were. And it would be built entirely from the top. That’s the part that sounds impossible. Every bridge you’ve ever seen built had cranes standing on the ground, trucks driving underneath it, and scaffolding climbing up from below.
Linn Cove would have none of that. No access road would be cut across the slope. No trucks would drive under the work. The only place anybody would touch the mountain was at the foot of each pier.
Here’s how you build a bridge without ever standing under it. Start with the end you already have. At the south end of the gap, where the finished road stopped, the contractor, Jasper Construction of Plymouth, Minnesota, set up a casting yard, an indoor plant on the mountainside where the pieces of the bridge would be made. It stood on the spot where the Viaduct’s visitor center stands today.
The bridge was born right next to the place it would go. Each piece was a hollow box of reinforced concrete about eight and a half feet long and as wide as the roadway, and each one weighed about fifty tons. There would be 153 of them. And because the bridge curved and twisted around the mountain in that S shape, rising and banking as it went, almost every one of those pieces had to be a slightly different shape from all the others.
Out of the 153, only one, segment number 93, is straight and square. Every other one is cut to a curve. Then the pieces went out along the bridge itself. A stiff-legged crane sat on the end of the finished deck.
A carriage brought each new segment out to it along the top of the bridge that already existed. The crane swung the segment out past the edge, over the open air and the boulders below, and held it against the face of the last one. The joint was coated with epoxy glue, and steel tendons running through the boxes were pulled tight, squeezing the new segment against the old so hard that the two became one piece of concrete. Then the crane rolled forward onto the segment it had just placed and reached for the next one.
The tendons are the secret of the whole thing. Think of a string of wooden beads. Lay them loose on a table, and you can bend the string any way you like. Pull the string tight and knot it, and the beads lock against each other into one stiff rod.
Every segment on Linn Cove is a bead, and the steel inside them is the string, pulled so tight that 153 separate boxes behave like a single beam. It’s like building a diving board out over a pool, one plank at a time, while standing on the end of the board. Every plank you add becomes the floor you stand on to add the next. And like a diving board, the end of it wants to droop.
A bridge reaching out over the air can only stretch so far before it needs something underneath. That’s what the piers were for. There are seven of them along the viaduct, spaced about 180 feet apart. Even the piers were built from the top.
Their foundations rest on micro-shaft piles, narrow shafts drilled down through the boulders into the solid rock beneath. Drilling those shafts was the only work done on the ground, and it was the only disturbance of the boulder field in the whole job. While the bridge reached out from one pier to the next, temporary cables held up the reaching end until it landed on the next pier. Somebody had to watch every one of those segments go out.
That person, for the federal government, was Rex Kraftoft, the Federal Highway Administration’s chief supervising engineer on the project. His job was to make sure that what was being hung off the side of Grandfather Mountain was built the way it had been drawn. Think about what that drawing asked for. 153 pieces, nearly all different, each cast in a yard and carried out over the void.
Each one landing against the last one, in a curve that had to come out right at the far end, with nothing beneath it to adjust. If one segment came out a little off, every segment after it would carry the mistake farther out into the air. On a bridge built from the ground, you can fix a mistake from underneath. You jack up a beam, you shim a bearing, you bring in a crane from below.
On Linn Cove, there was no underneath to work from. The only way to keep the curve true was to get every piece right before it ever left the casting yard, because once it was glued and pulled tight against the last one, it was the bridge. That’s why the shape of every segment mattered so much. In this kind of construction, each segment is normally cast right against the face of the one that will sit beside it, so the two would match exactly when they met in the air.
Out of that whole chain of 153 fits, the bridge had to end where the solid ground at the north end was waiting for it. Construction started in 1979, one fifty-ton segment at a time. The bridge reached across Linn Cove. The contract had been bid at about $7.
9 million. When it was done, the final cost was about $9. 8 million. Close to ten million dollars for a little over 1,200 feet of road.
Remember the budget from 1933, $16 million for all 469 miles. Half a century later, this one bridge, a quarter of a mile long, cost well over half of that. And when it was done, the park service says, the viaduct was completed without a single structural problem. Not one crack.
By 1983, the bridge was finished. The crane had walked all the way across the boulder field on the road it had built for itself and set down on the solid ground at the other end. Every one of those fifty-ton boxes had gone out over the rocks, and not one had been set down on them. But the parkway still wasn’t open.
The bridge was only one piece of the missing seven miles, and the rest of the link still had to be graded, curbed, and finished to the standard of the road on either side. So for another four years, the most famous bridge on the Parkway sat finished and closed, while drivers kept getting sent around the mountain on 221. You could stand at the end of the old road and see it, a gray curve hanging on the side of Grandfather Mountain, finished and empty, with no cars on it at all. Nobody had to wait to judge the bridge, though.
In 1984, the viaduct received a Presidential Design Award, one of more than a dozen national awards it would collect. Then they chose the date on purpose. On Friday, September 11th, 1987, the missing link around Grandfather Mountain opened to traffic, and with it, the Blue Ridge Parkway became one continuous road for the first time. September 11th, 1987 was exactly fifty-two years to the day after the Wednesday morning when the men from the relief rolls had started unloading Turrentine’s machinery at Low Gap.
The road that began eight days late on its first job closed its last gap right on the anniversary. Fifty-two years. Picture who was there at each end. The men who dragged those first steam shovels into place in 1935 were mostly young men out of work in the Depression.
The drivers who rolled across the Linn Cove Viaduct that September could have been their grandchildren. The road spanned the working lives of an entire generation, and some of the people who started it never saw it finished. It had cost a war’s worth of delay, a storm that killed dozens of people in the mountains around it, and thirteen years of a standoff over a single mountain. And at the very end, the last 1,200 feet were built without anybody ever setting foot on the ground they crossed.
But a road on a mountain is never really finished. The mountain still has the last word. And thirty-seven years later, it used it. In late September of 2024, Hurricane Helene came ashore in Florida as a Category 4 storm and drove north straight into the southern Appalachians.
In parts of the Blue Ridge, it dropped as much as thirty inches of rain. In 1940, the landslides that followed twenty inches at Idlewild had been called a once-in-a-century event. Helene brought more rain than that to the same mountains less than a century later. The ground did what it had done in 1940, only bigger.
Along the parkway, the park service counted fifty-eight catastrophic landslides. Whole sections of the road were undercut and slid away down the mountain, and at least one of the old tunnels was damaged. For the first time in its history, 100 percent of the Blue Ridge Parkway was closed. All 469 miles, from Virginia to the Smokies, the road that had taken fifty-two years to connect, was shut in a matter of days.
The worst of it landed in a stretch from Linville Falls at milepost 317 south toward Mount Mitchell State Park. That’s the high country just south of Grandfather Mountain, the hardest ground on the whole route, the same ground that had held the road up the longest the first time. Near Linville Falls alone, in a stretch of about thirty-eight miles, the park service documented more than four dozen landslides, and some of them were stacked on top of each other along the road, which meant the crews couldn’t simply pick the worst one and start. Rachel Stacy, the Parkway’s acting superintendent, put it plainly: “Some of the slides are actually inaccessible until you fix other slides.
You have to fix them sequentially. ”
That’s the old problem of the ridge again. On a road along a crest, there’s no detour for the trucks. To reach the slide at the far end, you have to rebuild the road through the slide in front of it first.
The way they’re rebuilding many of those slopes is called a reinforced soil slope. The park service describes it as looking somewhat like a tiered cake, only made of gravel and wire mesh. Crews dig out the failed ground, build the slope back up in layers of stone wrapped and tied in wire, cover it with topsoil, plant it, and then lay the road back across the top. It’s the drainage lesson of 1940, built in steel this time.
Let the water through, hold the mountain together, and put the road on top of it. One of those repair zones runs from milepost 318. 2 to 323. That’s the very spot where the park service photographer found a slide across the brand-new road on August 16th, 1940.
Eighty-four years apart, the mountain came down on that same stretch of road. On October 11th, 2024, the first sections began to reopen. By October 30th, the crews had finished clearing the debris at milepost 390. 4.
In its first year of recovery, the park service counted 350,000 cubic yards of debris hauled off the road, and more than 22,600 hours given by volunteers who came to help put their road back. By the fall of 2025, more than 400 miles were back open. In September of 2025, the stretch to Craggy Gardens and Mount Mitchell reopened, and drivers could once again go all the way from Cherokee up past the Pisgah Inn to Mount Mitchell. All 217 miles in Virginia came back.
The Federal Highway Administration put $25 million of emergency relief money into the work, and Congress set aside more than $2 billion in disaster funding for the park service. The last of the worst-hit miles, between Linville Falls and Mount Mitchell, are scheduled to be finished by the end of 2026. Right now, the Blue Ridge Parkway is being built again. The young men who graded the parkway’s slopes in those first camps went on to build 800 state parks across the country.
And the boulders are still down there under the Linn Cove Viaduct today, exactly where the mountain left them.